Summary of Introducing Business ProjectIn Hulunbeir City
| Project Name |
Lingdong Shaft Zalainuoer Coal Limited Company |
| Project Unit |
Zalainuoer Coal Limited Company |
| Project (Enterprise) Brief Introduction |
There 4 mines of the company right now, whose output is 5,970,000 ton; the producing value is 358,130,000Yuan; the enterprise asset is 1,428,380,000Yuan; debt is 551,280,000; after allowance, the profit is 7,060,000Yuan. |
| Construction Content |
It is to build up a large scale high-yield mine, which should have integrated digging equipments with large scale pulling pan. |
| Construction Conditions |
The industrial coal reserves is 1,374,000,000 ton in the coalmine, including 890,000,000 long flame coal with simple frame of coal bed. The mine has maturating basic mining conditions with mine rail, road, water and electricity supply. |
| Investment Dimensions and Finance Assessment |
Overall investment: 10,000,000,000Yuan, Fixed assets investment: 935,000,000Yuan; Current capital investment:51,370,000Yuan; Income of business: 5,500,000,000Yuan; Rate of investment return: 25.64%; Period of recovering investment: 8.04 year; Fiancial net output value:511,980,000 Yuan. |
| Venture Analysis and Market Forecast |
Market matters: a 2¡Á200000KW power plant is being built until now, A 2¡Á300000KW power plant is about to be built; two 4¡Á600000KW power plants are on the planing, one¡¯s scientific researching report of which has been finished, another¡¯s scientific researching report is on the writing. Therefore, on the base of the analysis of the local electricity building, the conclusion is that: there a large need of the coal in the market, stable resources, maturated technics, and excellent cooperating conditions. |
| Finished Work |
Having been listed into the nation approved Overall Mining Developing Programming, finished Scientific and Practical Researching Report, verified by the government of Inner Mongolia, passed project assessment by the National Developing and Reforming Committee. |
| Way of Cooperation |
Stock Cooperation; Multi-Financing. |
| Contact Way |
Contact Person£ºZhang Fengquan Telephone£º0470¡ª6562052 Fax£º0470¡ª6536258 Post Code£º021412 E-mail: www.zmgsqhb@mial.china.com Address£º17# Yulin Street Zalainuoer District of Man Zhouli City Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
500000 ton/year ¡°turning coal into oil¡± project of Zalainuoer Coal Limited Company |
| Project Unit |
Zalainuoer Coal Limited Company |
| Project (Enterprise) Brief Introduction |
There are 4 mines of the company right now, whose output is 5,970,000 ton, the producing value 358,130,000Yuan, the enterprise asset 1,428,380,000Yuan, debt 551,280,000 Yuan. After allowance, the profit is 7,060,000Yuan. |
| Construction Content |
It is to build up a coal liquefying processing factory to produce500000 ton oil products a year. |
| Construction Conditions |
For the pure coal, the gas transforming added hydrogen rate (95%) and producing oil rate (60%) are both high, after researching and demonstrating by the Coal Science Institute of China. So the coal is the excellent resource for liquefying coal. |
| Investment Dimensions and Finance Assessment |
Overall investment: 4,000,000,000Yuan, Income of sale: 940,000,000Yuan: Internal rate of return: 12%; Period of recovering investment: 8year; |
| Venture Analysis and Market Forecast |
It is a certain trend to make oil from coal for the lack of crude oil in China, so the project is a vast market. The project is built on the base of large-scale lignite mine, which provide enough material supply. Following the direction of industry development in China, the project can share a series of policy benefit. There will not have any policy venture. |
| Finished Work |
Possessing project suggestion report, having been listed into the energy sources developing programming of Inner Mongolia. |
| Way of Cooperation |
Stock Cooperation; Multi-Financing. |
| Contact Way |
Contact Person£ºZhang Fengquan Telephone£º0470¡ª6562052 Fax£º0470¡ª6536258 Post Code£º021412 E-mail: www.zmgsqhb@mial.china.com/ Address£º17# Yulin Street Zalainuoer District of Man Zhouli City Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
600,000 ton/year Making Carbinol from Coal Project of Zalainuoer Coal Limited Company |
| Project Unit |
Zalainuoer Coal Limited Company |
| Project (Enterprise) Brief Introduction |
There are 4 mines of the company right now, whose output is 5,970,000 ton, the producing value 358,130,000Yuan, the enterprise asset 1,428,380,000Yuan, debt 551,280,000. After allowance, the profit is 7,060,000Yuan. |
| Construction Content |
Making Carbinol from Coal Project needs the technics: gasifying, composing, rectifying, boiler vapor making |
| Construction Conditions |
The lignitic water element (Mt) is 30%, the lignitic ash element (Ad) 12 %, dry non-ash volatilization(Vdaf) 43%. The lignite is perfect chemistry industrial resource coal for the projects of direct coal liquefying, project of indirect coal liquefying and the project of composing carbinol after coal gasifying. |
| Investment Dimensions and Finance Assessment |
Overall investment: 1,820,000,000Yuan, Overall income of sale: 1200,000,000Yuan, Period of recovering investment: 5.5 year; |
| Venture Analysis and Market Forecast |
The product of the project is pure carbinol, which is a kind of well-sold important basic chemistry materials and engine side-fuel. We keep the balance of the need and supply by importing the carbinol in China, so there is no sale venture. |
| Finished Work |
Possessing suggestion script, the project has been agreed by the Inner Mongolia Government. |
| Way of Cooperation |
Stock Cooperation; Multi-Financing. |
| Contact Way |
Contact Person£ºZhang Fengquan Telephone£º0470¡ª6562052 Fax£º0470¡ª6536258 Post Code£º021412 E-mail: www.zmgsqhb@mial.china.com/ Address£º17# Yulin Street Zalainuoer District of Man Zhouli City Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
2¡Á300MW supper firepower power plant of Melidawa Autonomous Banner Inner Mongolia |
| Project Unit |
Government of Melidawa Autonomous Banner |
| Project (Enterprise) Brief Introduction |
The address of the project is adopted in the Nierji town of Inner Mongolia. Melidawa Banner input electricity from Haladong electricity transfer site (220KV) of the electricity net in Northeast of China. There are two 110KW electricity transfer sites and six 35KW electricity transfer sites, whose task is to provide partly electricity supply to Melidawa Autonomous Banner and Erlunchun Autonomous Banner. Amount of the electricity supply is 100,000,000KWH a year. For the electricity bulk sale, the price is very high, which restrict the industry (especially the large-scale industry) development of the autonomous banner. |
| Construction Content |
The project is to build up a 2¡Á300MW-firepower power plant one time, whose capacity is 600MW, with a reserved 2¡Á300MW construction scale. |
| Construction Conditions |
The supper firepower power plant intends to use the coal of Yimin coal mine 520 kilometer away with 5,000,000 ton output, which can meet the need of the plant. The electricity consumption of the banner had cumulated up to 100,000,000kwh, and it is forecast that the electricity consumption will be 200,000, 000kwh. The banner is planning to build up an industrial silicon project that will need 4,050,000,000kwh a year. |
| Investment Dimensions and Finance Assessment |
Static investment: 2,040,000,000Yuan; Dynamic investment: 2,350,000,000Yuan; Estimated unit price: 0.22Yuan/KWH (materials transported by truck, 0.15 Yuan/KWH (materials transported by train); investment internal rate of earning: 8%. |
| Venture Analysis and Market Forecast |
It is a low venture investment project. |
| Finished Work |
Having made up project suggestion report. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person£ºZhou Chunhui Telephone£º0470¡ª4613992 Fax£º0470¡ª4622804 Post Code£º162850 Address: Economy Bureau of Melidawa Autonomous Banner Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
720,000-ton Polyvinyl Chloride (PVC) Project of Melidawa Autonomous Banner Inner Mongolia |
| Project Unit |
Government of Melidawa Autonomous Banner |
| Project (Enterprise) Brief Introduction |
Polyvinyl Chloride can be used as the materials of architecture, electron, and packaging. It has been widely applied in the areas of industry, agriculture, architecture and transportation. In this project, Polyvinyl Chloride is made from limestone by calcium carbide method. |
| Construction Content |
720,000 ton/year Polyvinyl Chloride (PVC) Project will be built in the industrial district of Melidawa Banner£¬to purchase advanced equipment and build up workshop¡£ |
| Construction Conditions |
1. Electric power: Melidawa Autonomous Banner is planing to build up a 2¡Á300MW firepower plant which can produce 3,600,000,000 kWh, and Zhalantun City is planting to build a 4¡Á300MW power plant, which we can have a special electricity line to connect with. 2.Limestone: in Dengke town of our banner, there is a plenty of limestone with reserves of 184,000 ton, which contains 54.57% calcium oxide and 97.38% calcium carbonate. There also is plenty of limestone that reaches the PVC producing standard in nearby Arrange banner and Zalantun city. 3. Coke and blind coal: the proved coal reserves is 30,670,000,000 ton, estimated coal reserves 100,000,000,000 ton, which can meet the need of the project. |
| Investment Dimensions and Finance Assessment |
Overall investment: 1,590,000,000Yuan; Constructing investment: 425,000,000Yuan; Equipment investment: 1,022,000,000Yuan; Current investment: 141,000,000 Yuan; Other expense investment: 200,000Yuan; Product profit: 3,130,000,000Yuan; Rate of investment return: 50.9%; Period of recovering investment: a half year. |
| Venture Analysis and Market Forecast |
It is a low venture investment project. |
| Finished Work |
Having made up project suggestion report. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person£ºZhou Chunhui Telephone£º0470¡ª4613992 Fax£º0470¡ª4622804 Post Code£º162850 Address: Economy Bureau of Melidawa Autonomous Banner Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
300,000 ton/year Industry Silicon Project of Melidawa Autonomous Banner Inner Mongolia |
| Project Unit |
Government of Melidawa Autonomous Banner |
| Project (Enterprise) Brief Introduction |
We are pledge to build our region to an industry silicon producing base of China according to the ¡°115¡± programming. Industry silicon is used to aluminium alloy, which can be applied in manufacturing of vehicle, shipping, electron, and aviation-craft. Industry silicon is used in chemistry industry to produce the organic silicon compound, such as, silicon oil, silicone, silicon latex and so on. Industry silicon can also be used in iron and steel industry to make silicon iron. Industry silicon can be used to make single-crystal silicon, multi- crystal silicon which are the materials of making semiconductor. |
| Construction Content |
To build up a 300,000 ton/year Industry Silicon Factory in Melidawa Autonomous Banner |
| Construction Conditions |
1. There is plenty of silex resources in our banner with reserves 13,300,000 ton whose content of sio2 reaches 98.5%. 2. Our banner has rich electricity resource, a 2x300MW power plant will be built with output 3,600,000,000 kWh. 3. Charcoal resource is rich: the woods within the banner can provide 900,000 stere wood, then 150,000 stere charcoal. 4. Oil resource is rich: it is convenient to purchase oil from here. 5. Coal: proved coal reserves is 30,700,000,000 ton, and estimated coal reserves 100,000,000,000 ton, which can meet the need of the project. 6. Water conservancy: there are 56 rivers with water source of 16,480,000,000 stere. |
| Investment Dimensions and Finance Assessment |
Overall investment: 620,000,000Yuan; Including constructing and others¡¯ expense investment: 146,000,000Yuan, Equipment investment: 375,000,000Yuan; Current investment: 9,9240,000 Yuan; Rate of investment return: 50.9%; Period of recovering investment: 4 year; Balance output of profit and loss: 6,630,000 ton. |
| Venture Analysis and Market Forecast |
The project has perfect future |
| Finished Work |
Having made up project suggestion report. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person£ºZhou Chunhui Telephone£º0470¡ª4613992 Fax£º0470¡ª4622804 Post Code£º162850 Address: Economy Bureau of Melidawa Autonomous Banner Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
Alihe Supper Coal-Fire Power Plant £¨2¡Á300MW£© |
| Project Unit |
Economy Bureau of Erlunchun Autonomous Banner |
| Project (Enterprise) Brief Introduction |
During the period of ¡°115¡±, Erlunchun Autonomous Banner will be pressed for electricity power as many mine exploitations and the peocessing projects start to work. There will start the Mines exploiting of lead-zinc, silex and iron ore, and processing projects of soy, meat, milk, feedingstuff, starch. To build up the local power plant will be a good approach to solve the conflict of power requirement and supply. |
| Construction Content |
The project is to build up a 2¡Á300MW coal-fire power plant. |
| Construction Conditions |
In the vast zone of Erlunchun Autonomous Banner, there are more than 20 kinds of worthy mines, especially, coal mine in Dayangshu town, coal mine in the nearby within 100 kilometers region of Guli, Chun Tinghe, Wuzhigou. Building power station is the most effective and convenient approach to transform the first energy sources to the second energy sources. The electricity from this power station will all be used in the high-energy-consumption projects that will be started recently, such as, the projects of processing calcium carbide and PVC, as can transfer the source advantage to the economic advantage of Erlunchun Autonomous Banner. |
| Investment Dimensions and Finance Assessment |
Static investment: 2,700,000,000Yuan; Unit static investment: 4500Yuan/KM; Current capital investment: 3,159,000,000RMKB; Unit current capital investment: 5265 Yuan. 3,300,000,000KWH electricity will be produced in a year. Power price in power net: 0.33Yuan/kwh; Production value a year: 990,000,000Yuan; Tax a year:277£¬000£¬000Yuan; Internal rate of return: 8.68%. Rate paying of investment tax: 10.3%; Period of recovering investment: 13.63 year. |
| Venture Analysis and Market Forecast |
It is a low venture investment project. |
| Finished Work |
Having made up project suggestion report. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person£ºGao Chunqi, Wanping Telephone£º0470¡ª2248645 Fax£º0470¡ª224844 Post Code£º165450 E-mail: dwzsb2248645@163.com Address: Economy and Trade Bureau of Erlunchun Banner Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
1-Millon Ton Calcium Carbide Project of Arong Banner |
| Project Unit |
Economy Bureau of Arong Banner |
| Project (Enterprise) Brief Introduction |
From local abundant limestone source, the project can produce 1-milion ton calcium carbide, which is the material supply for the polyvinyl chloride (PVC) producing plant in lower reaches of a river. |
| Construction Content |
Lime is produced in ten 27-meter-tall limekilns with 5 meters inner diameter. The lime will be made into calcium carbide in twenty 2550KVA electric airtight stoves. The project can produce 100,000 ton excellent calcium carbide. |
| Construction Conditions |
Arong Banner is rich in limestone source with proved reserves of 114,000,000 ton and estimated reserves of 5,000,000,000 ton, whose CaO content reaches as high as 53.76%. The limestone is the excellent materials to produce calcium carbide. The earlier the resources are exploited, the more will benefit the local economy and industry development. |
| Investment Dimensions and Finance Assessment |
Overall project investment: 2,038,720,000Yuan, Including, fixed assets investment: 1,852,240,000Yuan, Current capital investment:186,480,000 Yuan; Sale tax and its appending a year: 125,250,000 Yuan; Annual average investment profit: 324,850,000Yuan; Rate of investment return:15.93%; Rate of tax return: 22.08%; Period of recovering investment: 6.41 year. |
| Venture Analysis and Market Forecast |
Calcium carbide is very important in the organic composing chemistry industry. It is also widely needed in metallurgy, building material and light industries. Recently, the overall output of calcium carbide is 17,000,000 ton in China, which can meet the need of organic chemistry industry. |
| Finished Work |
Having finished project suggestion report. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person£ºZhu Guilin Song Liangdong Telephone£º0470¡ª4210993 Post Code: 162750 Address£ºEconomy and Trade Bureau of Arong Banner Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
720,000 ton /year Polyvinyl Chloride (PVC) Project of Arong Banner |
| Project Unit |
Economy Bureau of Arong Banner |
| Project (Enterprise) Brief Introduction |
We can make the best of limestone source in Arong Banner by the PVC Project which can produce 720,000 ton Polyvinyl Chloride. Its construction needs little investment by the simple and effective technics of calcium carbide method to produce PVC. |
| Construction Content |
The Calcium Carbide Method PVC Project that can produce 720,000 ton Polyvinyl Chloride with suspending manufacturing technics. |
| Construction Conditions |
According to the long-term programming of industry district of Arong Banner, the 720,000 ton Calcium Carbide Method PVC Project can make the best use of the resources of calcium carbide, chlorine, hydrogen, water, power within the industry district. The project can not only cut down the sale stage but also guarantee the calcium carbide transforming in a short time, reducing the loss of calcium carbide pulverization in the PVC producing. |
| Investment Dimensions and Finance Assessment |
Overall project investment: 3,128,640,000 Yuan, Including, fixed assets investment: 2,840,640,000 Yuan, Current capital investment: 288,000,000Yuan; Income of sale a year: 5,400,000,000 Yuan; Overall profit: 958,210,000Yuan; Rate of investment return: 28.27%; Net output value: 3,246,020,000 Yuan; Rate of investment return: 30.63%. |
| Venture Analysis and Market Forecast |
In recent years, the consumption of Polyvinyl Chloride has rapidly increased in the market. It has been widely applied in the areas of industry, agriculture, architecture and transportation. We rely on the importation of PVC to meet the market need. The 720,000-ton Calcium Carbide Method PVC Project of Arong Banner adopted advanced technics to produce low-cost and high-quality product that can meet the market need. |
| Finished Work |
Having finished project suggestion report. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person£ºZhu Guilin Song Liangdong Telephone£º0470¡ª4210993 Post Code: 162750 Address£ºEconomy and Trade Bureau of Arong Banner Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
2¡Á300MW Coal-Fire Power Plant Project of Arong Banner |
| Project Unit |
Economy Bureau of Arong Banner |
| Project (Enterprise) Brief Introduction |
According to coal source of Hulunbeir City, the need of local economy development and the forecast to the electricity net of the East of Xinan Mountain and Northeast of China, Coal-Fire Power Plant Project of Arong Banner confirm its 2¡Á300MW power capacity, generating electricity 36¡Á105MWH a year, overall power supply 3,294,000,000KWH. |
| Construction Content |
To build up a 2¡Á300MW Coal-Fire Power Plant |
| Construction Conditions |
To make the best of the wealthy mine resource of Arong Banner and abundant coal resource, Arong Banner is planning to develop a series of heavy chemistry industries and high-energy consumption projects to transform resource advantage to economic advantage in recent years. On the preliminary calculation in advance, for the 2X300MW Coal-Fire Plant the cost of generating electricity is low, and the lower electricity sale price is competitive, which can promote the other industrial enterprise development. |
| Investment Dimensions and Finance Assessment |
Overall project investment: 2,802,300,000 Yuan, including, Fixed assets investment: 2,793,510,000 Yuan, Current capital investment: 8,790,000Yuan. Annual income of sale: 856,440,000 Yuan; Annual profit: 307,130,000 Yuan; Annual tax: 71,780,000 Yuan; Rate of investment return: 10.96%; Tax rate: 13.52%. |
| Venture Analysis and Market Forecast |
Arong Banner is planning to set up a series of high-energy consumption projects and large-scale industry projects to transform resource advantage to economic advantage in recent years. These are 250,000 ton industrial silicon project, 1- million ton calcium carbide project, 720,000 ton PVC project, and 1,700,000 ton cement project, which need electricity supply 4,000,000,000 kWh. So the project has the bright future in the market. |
| Finished Work |
Having finished project suggestion report. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person£ºZhu Guilin Song Liangdong Telephone£º0470¡ª4210993 Post Code: 162750 Address£ºEconomy and Trade Bureau of Arong Banner Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
Xihulitu Supper Coal-Fire Power Plant |
| Project Unit |
Developing and Reforming Bureau of Xinyou Banner |
| Project (Enterprise) Brief Introduction |
The proved coal reserves in Xihulitu coal mine is 1,388,190,000 ton, which can meet the need of 2¡Á300MW pithead power plant that require 2,750,000 ton coal a year. |
| Construction Content |
The project is to build up a 2¡Á300MW coal-fire power plant that can generate electricity 1,800,000,000 kWh. The mate constructions are 250000 ton silicon iron project and a 30000ton calcium carbide project. |
| Construction Conditions |
Estimated silica reserves is 50,000,000 ton, which can supply the material to a 250,000-ton silicon plant. |
| Investment Dimensions and Finance Assessment |
Allover project investment: 3,500,000,000Yuan; production value: 4,000,000,000Yuan; tax: 120,000,000 Yuan; Income of sale a year: 2,600,000,000 Yuan; Investment profit a year: 800,000,000 Yuan; Investment profit rate: 20%. |
| Venture Analysis and Market Forecast |
It can reduce the producing cost, for the crude coal can be transform at the pithead of coalmine. The cost of equipment¡¯s maintenance is low, which can have competitive electricity price. |
| Finished Work |
Having made up project suggestion report. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person: Zhang Huixia Telephone£º0470¡ª6401939 Fax£º0470¡ª6401877 Post Code£º021300 E-mail: xqzhaoshang@126.com Address: Developing and Reforming Bureau of Xinyou Banner Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
346,000 ton Silicon Iron Project of Zalantun City |
| Project Unit |
Economy Bureau of Zalantun City |
| Project (Enterprise) Brief Introduction |
Silicon iron is made out of silica and iron containing material. Silicon iron is a kind of carbon reductive product that is processed in electric heating stove with carbon reducer by the technics of electric heating continuous smelting and disconnectedly iron goes out. |
| Construction Content |
First building stage: eight 12500KVA silicon electric cooker, 74000ton/year designed producing capacity; four 25000KVA silicon cooker, 68000ton/year designed capacity; Second building stage: twelve 25000KVA silicon electric cookers, 204000ton/year designed producing capacity. After all the construction is completed, the project can produce 3,460,000,000 ton silicon 75#. |
| Construction Conditions |
Convenient traffic, abundant resources, policy supporting, enough power |
| Investment Dimensions and Finance Assessment |
Overall satatic investment: 1,075,000,000Yuan; Overall estimated investment: 1,200,000,000Yuan; First stage investment: 435,910,000 Yuan; second stage investment: 639,090,000 Yuan. The completed project can produce silicon iron 346,000 ton. Income of sale 1,350,000,000 Yuan; Investment profit 240,000,000 Yuan; Paying tax 60,000,000 Yuan a year. |
| Venture Analysis and Market Forecast |
The project has a bright market future. |
| Finished Work |
Individual investment, joint venture, cooperation |
| Way of Cooperation |
|
| Contact Way |
Contact Person£ºX¨¶Ning Telephone£º0470¡ª3211863 Fax£º0470¡ª3200863 Post Code£º162650 Address£ºEconomy Bureau of Zalantun City |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
2¡Á300,000KW Coal-Fire Power Plant Project of Zalantun City |
| Project Unit |
Hua Dian Power Corporation of China |
| Project (Enterprise) Brief Introduction |
Zanlantun will realize the connection with electricity net of Inner Mongolia by the 220kv electricity transmitting wire between Zalantun City and Wulanhaote City. There will build a 500,000kv double electricity transmitting wire between Yimin power plant and Daqing City, a 500,000kv-transformer substation to connect to electricity net of Northeast of China, which connect to the electricity net of North China and Mid China. All that can guarantee the power can transmit out of Inner Mongolia. |
| Construction Content |
According to the coal resources of Hulunbeir City and the need of local economy development, it is confirmed to build up a 2¡Á300,000KW Coal-Fire Power Plant |
| Construction Conditions |
There are excellent conditions for the project, such as, Convenient traffic, abundant resources, policy supporting, enough water, easily electricity out-transmitting. |
| Investment Dimensions and Finance Assessment |
Overall project investment: 3,000,000,000 Yuan; Annual tax: 300,000,000 Yuan Annual average production value: 900,000,000Yuan |
| Venture Analysis and Market Forecast |
The project has a bright developing future. |
| Finished Work |
Collecting the data of the project having been finished, suggestion report will be finished in recent time. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person£ºX¨¶Ning Telephone£º0470¡ª3211863 Fax£º0470¡ª3200863 Post Code£º162650 Address£ºEconomy Bureau of Zalantun City |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
2¡Á300MW Coal-Fire Power Plant Project of Genhe City |
| Project Unit |
Genhe Power Plant |
| Project (Enterprise) Brief Introduction |
There is an increasing energy need for the rapid economic development of China, especially, the Northeast of China. So, it is a direction for the coal resources¡¯ exploiting to supply Northeast Region clean and high-power electricity by building up large-scale pithead power plant in the eastern Inner Mongolia. |
| Construction Content |
The project plans to build the large capacity and high-parameter fire-power machines, which will make it to adjust the power construction to improve the equipment of northeast power net and keep its continuous development. |
| Construction Conditions |
There are excellent conditions for the project, such as, Convenient traffic, abundant resources, enough water resource, short distance to the coalmine. |
| Investment Dimensions and Finance Assessment |
The project plans to produce 3,300,000,000 kWh a year; Overall project fixed investment: 2,700,000,000Yuan; Fixed unit investment: 4500Yuan/kw; Project current capital investment: 3,159,000,000Yuan; Current capital investment:5265Yuan/kw; Annual production value: 990,000,000 Yuan; Annual sale profit: 448,580,000 Yuan; Project internal financial yield rate: 9.75%; Project financial net output value(ic=12%): 289,184,100Yuan; Period of recovering investment: 9.7 year; |
| Venture Analysis and Market Forecast |
Through the investment estimating reckon and economic analysis, the project reaches the national economic and technic guidelines. It is low venture project for the competitive power price for supplying to the powernet. From the financial analysis, the project is approved. |
| Finished Work |
Having finished project suggestion report. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person£ºHanlei Telephone£º0470¡ª5222636 Fax: 0470-5222175 Post Code: 022350 E-mail: Yan ying542@tom.com Address£ºDeveloping and Reforming Bureau of Genhe City Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
1Millon Ton Calcium Carbide Project of Elunchun Autonomous Banner |
| Project Unit |
Economy Bureau of Elunchun Autonomous Banner |
| Project (Enterprise) Brief Introduction |
The Jiwen town of Elunchun Autonomous Banner is rich in limestone source with proved reserves of 70,000,000 ton and estimated reserves of 200,000,000 ton, whose CaO content reaches as more than 53.76%. The limestone is the excellent materials to produce calcium carbide. It is necessary to build up the 1Millon Ton Calcium Carbide Project to fully exploit the local limestone, consume the superfluous power of the banner and transform the resource advantage to economic advantage. |
| Construction Content |
The project can produce 100,000 ton excellent calcium carbide. It need to build up twenty-five 20000KVA electric airtight stone stoves. |
| Construction Conditions |
The project will be set in the Jiwen town of Elunchun Autonomous Banner with 60-hectare area, which is rich in limestone source. There are Yi-Jia railway and 301 national road through the project region, telephones that deal to anywhere of China, and good basic establishments. |
| Investment Dimensions and Finance Assessment |
Overall project investment: 542,750,000 Yuan, Including, fixed assets investment: 495,000,000 Yuan, Current capital investment: 47,750,000Yuan. |
| Venture Analysis and Market Forecast |
Annual tax: 410,017,500Yuan; Rate of paying tax:75.5%; Rate of investment return: 58.7%; annual average investment profit: 318,660,000Yuan; Period of recovering investment: 3.54 year. |
| Finished Work |
Having finished project suggestion report. |
| Way of Cooperation |
Individual investment, joint venture, cooperation |
| Contact Way |
Contact Person£ºGao Chunqi Wanping Telephone£º0470¡ª2248645 Fax: 0470-2248644 Post Code: 165450 E-mail: dwzsb2248645@163.com Address£ºEconomy and Trade Bureau of Elunchun Autonomous Banner Inner Mongolia |
Summary of Introducing Business Project In Hulunbeir City
| Project Name |
Amine Initial Medicine Cream Product Line expanding Project |
| Project Unit |
Hongyu Agricultural Drug Limited Company Inner Mongolia |
| Project (Enterprise) Brief Introduction |
Hongyu Agricultural Drug Limited Company Inner Mongolia is a agricultural drug producing company approved by national chemistry industry bureau, and the only one company to compose pesticide. Its high-quality and low-price product is very popular in the market, and has been exported into the European market. The company with high-teachnics has a producing capacity of 15000 ton a year. |
| Construction Content |
To build a 20000-ton product line that can produce 96% amine and 99% amine initial chemical cream. |
| Construction Conditions |
With high technic and good traffic conditions, the company has the independent knowledge property right of the product, which has been exported in the European countries. Its product is one third (1/3) lower than the national and inter-national products. |
| Investment Dimensions and Finance Assessment |
Overall project investment: 176,000,000 Yuan, including, fixed assets investment: 95,200,000 Yuan, Current capital investment: 80,800,000Yuan. Increased Income of sale 800,000,000 Yuan; Tax paying: 100,000,000 Yuan; Investment profit rate: 41.72%; Investment profit tax rate: 62.8%; Period of recovering investment: 4,42 year(before tax); 5,55year (after tax).< |